Greenspot

  • Date Completed: February 2015
  • Project Location: Highland, CA
  • Project Category: substructures
  • Project Owner: SCE Transmission

International Line Builders placed eight 10 foot x 20 foot vaults and 6,900 feet of trench with six 5-inch concrete encased duct bank. This underground system was built for the removal of a section of 33kV and 66kV overhead lines.